Act/Law wise: Judgment of Supreme Court of India



Arbitration Matter
Section/Order/ Article/Rule/ Regulation Head Note Parties Name Reference/Citation
Arbitration––

Arbitration–– The arbitration clause in the main contract states that the disputes which are to be referred to the committee of three arbitrators under Clause 67.3 are disputes in regard to which the decision of the Engineer (“Engineer” refers to person appointed by the State of Kerala to act as Engineer for the purpose of the contract between the PW Department and the respondent) has not become final and binding pursuant to Clause 67.1 or disputes in regard to which amicable settlement has not been reached between the State of Kerala and the respondent within the period stated in Clause 67.2. Obviously neither Clause 67.1 nor 67.2 will apply as the question of “Engineer” issuing any decision in a dispute between the contractor and the sub-contractor, or any negotiations being held with the Engineer in regard to the disputes between the contractor and the subcontractor does not arise. The position would have been quite different if the arbitration clause had used the words “all disputes arising between the parties” or “all disputes arising under this contract”. Secondly, the arbitration clause contemplates a committee of three arbitrators, one each to be appointed by the State of Kerala and the respondent and the third (Chairman) to be nominated by the Director General, Road Development, Ministry of Surface Transport, Roads Wing, Government of India. There is no question of such nomination in the case of a dispute between the contractor and the sub-contractor.” .....M/S. Elite Engineering & Construction (Hyd.) Pvt. Ltd.=VS=M/S. Techtrans Construction, [4 LM (SC) 66] ....View Full Judgment

M/S. Elite Engineering & Construction (Hyd.) Pvt. Ltd.=VS=M/S. Techtrans Construction 4 LM (SC) 66
The appointment of an Arbitrator

The appointment of an Arbitrator as per Clause 11.12 of the 2007 Scheme–– In the instant case, the learned Single Judge in the impugned Order has erroneously taken the view that an arbitration clause would not stand incorporated in the individual sale orders entered into by the Respondent No.2 – Coal Company and the Appellant. The individual sale orders emanate out of the 2007 Scheme. The sale orders specifically state that they would be governed by the guidelines, circulars, office orders, notices, instructions, relevant law etc. issued from time to time by Coal India Limited or Bharat Coking Coal Limited etc. As a consequence, the arbitration clause (i.e. Clause 11.12) in the 2007 Scheme would stand incorporated in the sale orders issued thereunder. Clause 7 in the sale orders falls under the ‘single contract case’ where the arbitration clause is contained in a standard form document i.e. the 2007 Scheme, to which there is a reference in the individual sale orders issued by Respondent No. 2 – the Coal Company. The arbitration clause in the 2007 Scheme clearly states that : “All disputes arising out of this scheme or in relation thereto in any form whatsoever shall be dealt exclusively by way of arbitration in terms of the Arbitration and Conciliation Act, 1996.” The view taken by the learned Single Judge is erroneous, and is hereby setaside. The appeal is allowed.
The parties consensually agreed to appoint Mr. Justice Pranab Kumar Chattopadhyay as Sole Arbitrator to adjudicate the disputes which have arisen between the Appellant and Respondent No. 2, under the 2007 Scheme. The appointment of Mr. Justice Chattopadhyay will be subject to the disclosure and declaration made, as per the Sixth Schedule to the Arbitration and Conciliation Act, 1996. ...Giriraj Garg =VS= Coal India Ltd., [6 LM (SC) 43] ....View Full Judgment

Giriraj Garg =VS= Coal India Ltd. 6 LM (SC) 43
Appointed as the Arbitrator––

Appointed as the Arbitrator–– The purchase order was issued by the Appellant in which it was categorically mentioned that the supply would be as per the terms mentioned therein and in the attached standard terms and conditions. The Respondent by his letter dated 15.12.2012 confirmed its acceptance of the terms and conditions mentioned in the purchase order except delivery period. The dispute arose after the delivery of the goods. No doubt, there is nothing forthcoming from the pleadings or the submissions made by the parties that the standard form attached to the purchase order is of a trade association or a professional body. However, the Respondent was aware of the standard terms and conditions which were attached to the purchase order. The purchase order is a single contract and general reference to the standard form even if it is not by a trade association or a professional body is sufficient for incorporation of the arbitration clause. The appeal is allowed and the judgment of the High Court is set aside. Justice Sushil Harkauli is appointed as the Arbitrator to adjudicate the dispute between the parties. .....M/S. Inox Wind Ltd. =VS= M/S Thermocables Ltd., [4 LM (SC) 73] ....View Full Judgment

M/S. Inox Wind Ltd. =VS= M/S Thermocables Ltd. 4 LM (SC) 73
Appointment of an Arbitrator–

The appointment of an Arbitrator as per Clause 11.12 of the 2007 Scheme–
In the instant case, the learned Single Judge in the impugned Order has erroneously taken the view that an arbitration clause would not stand incorporated in the individual sale orders entered into by the Respondent No.2 – Coal Company and the Appellant. The individual sale orders emanate out of the 2007 Scheme. The sale orders specifically state that they would be governed by the guidelines, circulars, office orders, notices, instructions, relevant law etc. issued from time to time by Coal India Limited or Bharat Coking Coal Limited etc. As a consequence, the arbitration clause (i.e. Clause 11.12) in the 2007 Scheme would stand incorporated in the sale orders issued thereunder. Clause 7 in the sale orders falls under the ‘single contract case’ where the arbitration clause is contained in a standard form document i.e. the 2007 Scheme, to which there is a reference in the individual sale orders issued by Respondent No. 2 – the Coal Company. The arbitration clause in the 2007 Scheme clearly states that : “All disputes arising out of this scheme or in relation thereto in any form whatsoever shall be dealt exclusively by way of arbitration in terms of the Arbitration and Conciliation Act, 1996.” The view taken by the learned Single Judge is erroneous, and is hereby setaside. The appeal is allowed.
The parties consensually agreed to appoint Mr. Justice Pranab Kumar Chattopadhyay as Sole Arbitrator to adjudicate the disputes which have arisen between the Appellant and Respondent No. 2, under the 2007 Scheme. The appointment of Mr. Justice Chattopadhyay will be subject to the disclosure and declaration made, as per the Sixth Schedule to the Arbitration and Conciliation Act, 1996. ...Giriraj Garg =VS= Coal India Ltd., (Civil), 2019 (1) [6 LM (SC) 43] ....View Full Judgment

Giriraj Garg =VS= Coal India Ltd. 6 LM (SC) 43